A consultant has recommended that you modernize a production line. Costs include $650,000 in equipment, a $10,000 investment in net working capital at the time of installation, and $5,000 in delivery and installation costs. The consultant has billed the firm for $7,500 for her analysis of the project. If the project is undertaken, an employee training program costing $8,000 would be required. The old machinery has no book value but can be sold for $100,000. Your firm's marginal tax rate is 34%. What is the initial outlay associated with the project?

a. $619,500
b. $612,000
c. $570,000
d. $578,000
e. $607,000

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 18:30, raquelwilliams6912
What’s the best type of healthcare plan
Answers: 1
image
Business, 21.06.2019 21:30, legrandschool1oxa0sd
The following information relates to wagner, inc.: advertising costs $ 18 comma 600 administrative salaries 17 comma 800 delivery vehicle depreciation 1 comma 500 factory repair and maintenance 600 indirect labor 10 comma 000 indirect materials 18 comma 000 manufacturing equipment depreciation 3 comma 000 office rent 58 comma 000 president's salary 1 comma 100 sales revenue 600 comma 000 sales salary 5 comma 200 how much were wagner's period costs
Answers: 3
image
Business, 22.06.2019 13:10, KillerSteamcar
A4-year project has an annual operating cash flow of $59,000. at the beginning of the project, $5,000 in net working capital was required, which will be recovered at the end of the project. the firm also spent $23,900 on equipment to start the project. this equipment will have a book value of $5,260 at the end of the project, but can be sold for $6,120. the tax rate is 35 percent. what is the year 4 cash flow?
Answers: 2
image
Business, 22.06.2019 19:00, lonelynomad00
Adrawback of short-term contracting as an alternative to making a component in-house is thata. it is the most-integrated alternative to performing an activity so the principal company has no control over the agent. b. the supplying firm has no incentive to make any transaction-specific investments to increase performance or quality. c. it fails to allow a long planning period that individual market transactions provide. d. the buying firm cannot demand lower prices due to the lack of a competitive bidding process.
Answers: 2
You know the right answer?
A consultant has recommended that you modernize a production line. Costs include $650,000 in equipme...

Questions in other subjects:

Konu
Mathematics, 22.07.2019 16:30