Cooper Construction Company had a contract starting April 2021, to construct a $24,000,000 building that is expected to be completed in September 2023, at an estimated cost of $22,000,000. At the end of 2021, the costs to date were $10,120,000 and the estimated total costs to complete had not changed. The progress billings during 2021 were $4,800,000 and the cash collected during 2021 was 3,200,000. Cooper uses the percentage-of-completion method.
For the year ended December 31, 2021, Cooper would recognize gross profit on the building of:
a) $843,333
b) $920,000
c) $1,080,000
d) $0

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 19:20, ellycleland16
Which of the following best explains why large companies have an advantage over smaller companies? a. economies of scale make it possible to offer lower prices. b. the production possibilities frontier is wider for a larger company. c. decreasing marginal utility enables more efficient production. d. increasing the scale of production leads to a reduction in inputs.2b2t
Answers: 1
image
Business, 22.06.2019 02:30, llama1314
Sweeten company had no jobs in progress at the beginning of march and no beginning inventories. the company has two manufacturing departments--molding and fabrication. it started, completed, and sold only two jobs during march—job p and job q. the following additional information is available for the company as a whole and for jobs p and q (all data and questions relate to the month of march): molding fabrication total estimated total machine-hours used 2,500 1,500 4,000 estimated total fixed manufacturing overhead $ 10,000 $ 15,000 $ 25,000 estimated variable manufacturing overhead per machine-hour $ 1.40 $ 2.20 job p job q direct materials $ 13,000 $ 8,000 direct labor cost $ 21,000 $ 7,500 actual machine-hours used: molding 1,700 800 fabrication 600 900 total 2,300 1,700 sweeten company had no underapplied or overapplied manufacturing overhead costs during the month. required: for questions 1-8, assume that sweeten company uses a plantwide predetermined overhead rate with machine-hours as the allocation base. for questions 9-15, assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both departments. 1. what was the company’s plantwide predetermined overhead rate? (round your answer to 2 decimal places.) next
Answers: 2
image
Business, 22.06.2019 10:00, tiarafaimealelei
The solution set for -18 < 5x-3 iso-3х3< xо-3хo3 > x
Answers: 3
image
Business, 22.06.2019 10:30, Uc34758
Issued to the joint planning and execution community (jpec) initiates the development of coas; it also requests that the supported ccdr submit a commander's estimate of the situation with a recommended coa to resolve the situation (joint force command and staff participation in the joint operation planning and execution system, page 10)
Answers: 2
You know the right answer?
Cooper Construction Company had a contract starting April 2021, to construct a $24,000,000 building...

Questions in other subjects:

Konu
World Languages, 13.03.2022 22:30