subject
Business, 17.04.2020 23:30 nelly88

The monthly demand for a part produced for an automotive final assembly plant is 16,000 units. There are 20 working days in February and the effective operating time of the plant is 900 min per day (two shifts). The fraction defect rate for the component is 0.017, and the automated machine that produces the part has an availability of 96%. Determine the takt time for this part.

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 12:30, nardosem9
Savvy sightseeing had beginning equity of $90,000; revenues of $144,000, expenses of $83,000, and dividends to stockholders of $10,800. there were no stockholder investments during the year. calculate ending equity.
Answers: 3
image
Business, 22.06.2019 09:00, tiffanibell71
Asap describe three different expenses associated with restaurants. choose one of these expenses, and discuss how a manager could handle this expense.
Answers: 1
image
Business, 22.06.2019 18:30, spazzinchicago
Health insurance protects you if you experience any of the following except: a: if you have to be hospitalized b: if you damage someone's property c: if you need to visit a clinic d: if you can't work because of illness
Answers: 2
image
Business, 23.06.2019 05:20, Geo777
What is difference between fiscal year and tax year? explain in the simplest way.
Answers: 1
You know the right answer?
The monthly demand for a part produced for an automotive final assembly plant is 16,000 units. There...