On March 1, 2017, Sheffield Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,330,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below:
2017 2018 2019
Contract costs incurred during the year $2,671,200 $2,193,000 $2,395,800
Estimated costs to complete the contract at 12/31 3,688,800 2,395,800 –0–
Billings to Fabrik during the year 3,170,000 3,510,000 1,650,000
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank.)
2017

Cost to Date (12/31/17)

$
Entry field with correct answer2671200

Entry field with correct answer Estimated Cost to Complete

Entry field with correct answer3688800

Entry field with correct answer Total Cost

$
Entry field with incorrect answer633600

Entry field with correct answer Percent to complete

Entry field with correct answer42

%
Entry field with correct answer Revenue Recognized

$
Entry field with incorrect answer2698600 (incorrect)

Entry field with correct answer Costs Incurred

Entry field with correct answer2671200

Entry field with correct answer Profit/ Loss Recognized in 2017

$
Entry field with incorrect answer27400 (inorrect)

2018

Entry field with correct answer Costs to date (12/31/18)

$
Entry field with correct answer4864200

Entry field with correct answer Estimated Costs to Complete

Entry field with incorrect answer2385800 (incorrect)

Entry field with correct answer Estimated Total Costs

$
Entry field with incorrect answer7250000

(incorrect)
Percent complete

Entry field with correct answer67

%
Entry field with correct answer Revenue Recognized in 2018

$
Entry field with correct answer2082500

Entry field with correct answer Costs Incurred in 2018

Entry field with correct answer2193000

Entry field with correct answer Profit / (Loss) Recognized in 2018

$
Entry field with correct answer(110500)

2019

Entry field with correct answer total Costs Incurred

$
Entry field with incorrect answer(INCORRECT)

Entry field with incorrect answer Profit Previously RecognizedTotal Costs IncurredProfit / (Loss) Recognized in 2019Total Revenue RecognizedTotal Profit on ContractEAT_1364799800488_0_2561446 869231341 (INOCRRECT)

Entry field with incorrect answer(INCORRECT)

Entry field with incorrect answer Total Profit on ContractProfit / (Loss) Recognized in 2019Profit Previously RecognizedTotal Costs IncurredTotal Revenue RecognizedEAT_1364799800488_0_54601 63114080155 (INCORRECT

Entry field with incorrect answer2748900 (INCORRECT)

Less

:
Entry field with incorrect answer Profit / (Loss) Recognized in 2019Total Revenue RecognizedTotal Costs IncurredTotal Profit on ContractProfit Previously RecognizedEAT_1364799800488_0_25614 46869231341 (INCORRECT)

Entry field with incorrect answer(INCORRECT

Entry field with correct answer Profit. (Loss) Recognized in 2019

$
Entry field with correct answer353100

(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e. g. -45 or parentheses e. g. (45).)
2017 $
Entry field with correct answer0

2018 $
Entry field with correct answer0

2019 $
Entry field with correct answer1070000

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 00:50, katie673
At a roundabout, you must yield to a. already in the roundaboutb. entering the roundaboutc. only if their turn signal is ond. only if they honk at you
Answers: 1
image
Business, 22.06.2019 19:30, kylierice1
Exercise 4-9presented below is information related to martinez corp. for the year 2017.net sales $1,399,500 write-off of inventory due to obsolescence $80,440cost of goods sold 788,200 depreciation expense omitted by accident in 2016 43,600selling expenses 65,800 casualty loss 53,900administrative expenses 53,500 cash dividends declared 43,300dividend revenue 22,100 retained earnings at december 31, 2016 1,042,400interest revenue 7,420 effective tax rate of 34% on all items exercise 4-9 presented below is information relateexercise 4-9 presented below is information relate prepare a multiple-step income statement for 2017. assume that 61,500 shares of common stock are outstanding. (round earnings per share to 2 decimal places, e. g. 1.49.)prepare a separate retained earnings statement for 2017. (list items that increase retained earnings first.)
Answers: 2
image
Business, 22.06.2019 23:30, autumnsusan190ox9kn4
Decision alternatives should be identified before decision criteria are established. are limited to quantitative solutions are evaluated as a part of the problem definition stage. are best generated by brain-storming.
Answers: 1
image
Business, 23.06.2019 07:30, chaaaa
Me this has caused me stress and my head hurts
Answers: 1
You know the right answer?
On March 1, 2017, Sheffield Construction Company contracted to construct a factory building for Fabr...

Questions in other subjects:

Konu
Advanced Placement (AP), 15.08.2021 17:20
Konu
Mathematics, 15.08.2021 17:20
Konu
Mathematics, 15.08.2021 17:20