A supplier to Ford stamps out parts using a press. Changing a part type requires the supplier to change the die on the press. This changeover currently takes four hours. The supplier estimates that each hour spent on the changeover costs $250. Demand for parts is 1,000 per month. Each part costs the supplier $100, and the supplier incurs an annual holding cost of 25%. Ford would like the supplier to reduce their batch size by a factor of four; that is, if the supplier currently produces Q parts per batch, Toyota would like them to produce Q/4 parts per batch. Based on what the supplier should modify in order to achieve this result, what must this correctly chosen value (C, H, R, or S) be in order to reduce the batch size by a factor of 4: (Your answer must be numbers only, no symbols or words specifying unit of measure. Given 3 of the options are dollar amounts, your answer must include two decimal places, even if they are zeros, regardless of whether it is a dollar amount or not).

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 20.06.2019 18:04, coochieboi
Before you begin to compose a message, you should conduct research to collect the necessary information. to avoid frustration and inaccurate messages, be sure to consider the receiver's position. which questions should you ask yourself before determining what and how to research?
Answers: 3
image
Business, 22.06.2019 18:20, fantasticratz2
Principals are an administration career
Answers: 2
image
Business, 22.06.2019 19:50, crzyemo865
Aproduction line has three machines a, b, and c, with reliabilities of .96, .86, and .85, respectively. the machines are arranged so that if one breaks down, the others must shut down. engineers are weighing two alternative designs for increasing the line’s reliability. plan 1 involves adding an identical backup line, and plan 2 involves providing a backup for each machine. in either case, three machines (a, b, and c) would be used with reliabilities equal to the original three. a. compute overall system reliability under plan 1. (round your intermediate calculations and final answer to 4 decimal places.) reliability b. compute overall system reliability under plan 2. (round your intermediate calculations and final answer to 4 decimal places.) reliability c. which plan will provide the higher reliability? plan2plan1
Answers: 3
image
Business, 22.06.2019 20:20, laidbackkiddo412
Tl & co. is following a related-linked diversification strategy, and soar inc. is following a related-constrained diversification strategy. how do the two firms differ from each other? a. soar inc. generates 70 percent of its revenues from its primary business, while tl & co. generates only 10 percent of its revenues from its primary business. b. soar inc. pursues a backward diversification strategy, while tl & co. pursues a forward diversification strategy. c. tl & co. will share fewer common competencies and resources between its various businesses when compared to soar inc. d. tl & co. pursues a differentiation strategy, and soar inc. pursues a cost-leadership strategy, to gain a competitive advantage.
Answers: 3
You know the right answer?
A supplier to Ford stamps out parts using a press. Changing a part type requires the supplier to cha...