Japan Company produces lamps that require 3 standard hours per unit at a standard hourly rate of $12.00 per hour. Production of 8,900 units required 26,170 hours at an hourly rate of $12.20 per hour. What is the direct labor

(a) rate variance,
(b) time variance, and
(c) total cost variance? Enter favorable variances as negative numbers.

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 01:30, gavinarcheroz2jxq
Consider the following limit order book for a share of stock. the last trade in the stock occurred at a price of $50. limit buy orders limit sell orders price shares price shares $49.75 500 $49.80 100 49.70 900 49.85 100 49.65 700 49.90 300 49.60 400 49.95 100 48.65 600 a. if a market buy order for 100 shares comes in, at what price will it be filled? (round your answer to 2 decimal places.) b. at what price would the next market buy order be filled? (round your answer to 2 decimal places.) c. if you were a security dealer, would you want to increase or decrease your inventory of this stock? increase decrease
Answers: 2
image
Business, 22.06.2019 05:50, Haddixhouse8948
Match each of the terms below with an example that fits the term. a. fungibility the production of gasoline b. inelasticity the switch from coffee to tea c. non-excludability the provision of national defense d. substitution the demand for cigarettes
Answers: 2
image
Business, 22.06.2019 10:00, silviamgarcia
Scenario: you have advised the owner of bond's gym that the best thing to do would be to raise the price of a monthly membership. the owner wants to know what may happen once this price increase goes into effect. what will most likely occur after the price of a monthly membership increases? check all that apply. current members will pay more per month. the quantity demanded for memberships will decrease. the number of available memberships will increase. the owner will make more money. bond's gym will receive more membership applications.
Answers: 1
image
Business, 22.06.2019 11:30, barn01
17.     chef a says that garnish should be added to a soup right before serving. chef b says that garnish should be cooked with the other ingredients in a soup. which chef is correct? a. chef a is correct. b. both chefs are correct. c. chef b is correct. d. neither chef is correct. student c   incorrect which is correct answer?
Answers: 2
You know the right answer?
Japan Company produces lamps that require 3 standard hours per unit at a standard hourly rate of $12...

Questions in other subjects:

Konu
Biology, 28.09.2021 02:10