You manage a project with 10 activities. Activities A1, A3, A5, A9 form the critical path. As you have a large budget for the project, you are considering crashing activity A2, which has the potential to shorten the time of A2 by 3 days What do you think about this opportunity?

a. A sood idea, it will reduce the rojet duation by 3 days
b. A bad idea, as A2 is not on the critical path

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 12:00, ajayrose
Describe the three different ways the argument section of a cover letter can be formatted
Answers: 1
image
Business, 22.06.2019 12:50, tayjohn9774
Kendrick is leaving his current position at a company, and charlize is taking over. kendrick set up his powerpoint for easy access for himself. charlize needs to work in the program that is easy for her to use. charlize should reset advanced options
Answers: 3
image
Business, 22.06.2019 19:50, Salas1333
Which of the following would create the most money? the initial deposit is $6,500 and the required reserve ratio is 20 percent. the initial deposit is $3,000 and the required reserve ratio is 10 percent. the initial deposit is $7,500 and the required reserve ratio is 25 percent. the initial deposit is $4,500 and the required reserve ratio is 15 percent.
Answers: 1
image
Business, 22.06.2019 21:10, ray1840
Ahospital purchases a $500,000 magnetic resonance imaging (mri) machine that has a useful life of 9 years. the salvage value at the end of 9 years is $77,000. (a) write a linear equation that describes the value y (in dollars) of the mri machine in terms of the time t (in years), 0 ≤ t ≤ 9. (b) find the value, in dollars, of the machine after 6 years. $ (c) find the time, in years, when the value of the equipment will be $140,000. (round your answer to two decimal places.) yr
Answers: 2
You know the right answer?
You manage a project with 10 activities. Activities A1, A3, A5, A9 form the critical path. As you ha...

Questions in other subjects:

Konu
Biology, 19.10.2019 22:50
Konu
Chemistry, 19.10.2019 22:50
Konu
Mathematics, 19.10.2019 22:50
Konu
English, 19.10.2019 22:50
Konu
History, 19.10.2019 22:50