A project has an original budget of US$1,000,000 and expected revenues of US$1,400,000. At a milestone, the project is forecasted to cost an additional US$300,000. If the project is cancelled, it will bring in no revenues but the cost will be limited to the US$600,000 already spent. If the project is continued, there is a 60 percent chance that the new budget will be met. If not, the budget will be further off by another US$300,000. What is the best option to take?

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 13:00, stelllllllllllllllla
Ronald works for a small biotech firm. when the firm presents the results of its clinical trials to the fda, ronald realizes that the results are not accurate. he reports this to the fda. ronald is a(n)
Answers: 3
image
Business, 22.06.2019 12:50, emarquez05
Two products, qi and vh, emerge from a joint process. product qi has been allocated $34,300 of the total joint costs of $55,000. a total of 2,900 units of product qi are produced from the joint process. product qi can be sold at the split-off point for $11 per unit, or it can be processed further for an additional total cost of $10,900 and then sold for $13 per unit. if product qi is processed further and sold, what would be the financial advantage (disadvantage) for the company compared with sale in its unprocessed form directly after the split-off point?
Answers: 2
image
Business, 22.06.2019 18:10, iris7324
During the year, the delph company had no beginning or ending inventories and it started, completed, and sold only two jobs—job d-75 and job c-100. it provided the following information related to those two jobs: job d-75: molding fabrication total direct materials cost $ 375,000 $ 325,000 $ 700,000 direct labor cost $ 200,000 $ 160,000 $ 360,000 machine-hours 15,000 5,000 20,000 job c-100: molding fabrication total direct materials cost $ 300,000 $ 250,000 $ 550,000 direct labor cost $ 175,000 $ 225,000 $ 400,000 machine-hours 5,000 25,000 30,000delph had no overapplied or underapplied manufacturing overhead during the year. assume delph uses a plantwide overhead rate based on machine-hours.1-a. compute the predetermined plantwide overhead rate.1-b. compute the total manufacturing costs assigned to job d-70 and job c-200.1-c. if delph establishes bid prices that are 150% of total manufacturing costs, what bid price would it have established for job d-70 and job c-200? 1-d. what is delph's cost of goods sold for the year? assume delph uses departmental overhead rates based on machine-hours.2-a. compute the predetermined departmental overhead rates.2-b. compute the total manufacturing costs assigned to job d-70 and job c-200.2-c. if delph establishes bid prices that are 150% of total manufacturing costs, what bid price would it have established for job d-70 and job c-200? 2-d. what is delph's cost of goods sold for the year?
Answers: 3
image
Business, 22.06.2019 19:00, michael1498
It is estimated that over 100,000 students will apply to the top 30 m. b.a. programs in the united states this year. a. using the concept of net present value and opportunity cost, when is it rational for an individual to pursue an m. b.a. degree. b. what would you expect to happen to the number of applicants if the starting salaries of managers with m. b.a. degrees remained constant but salaries of managers without such degrees decreased by 20 percent
Answers: 3
You know the right answer?
A project has an original budget of US$1,000,000 and expected revenues of US$1,400,000. At a milesto...