A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of $84,000. The software manager estimates a value completed of $81,000. What are the cost and schedule variances and CSI? Estimate the time variance.

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 18:20, kierafisher05
James sebenius, in his harvard business review article: six habits of merely effective negotiators, identifies six mistakes that negotiators make that keep them from solving the right problem. identify which mistake is being described. striving for a “win-win” agreement results in differences being overlooked that may result in joint gains.
Answers: 2
image
Business, 21.06.2019 22:40, itscheesycheedar
In allentown, pennsylvania, in the summer of 2014, the average price of a gallon of gasoline was $3.68long dasha 22-cent increase from the year before. many consumers were upset by the increase. one was quoted in a local newspaper as saying, "it's crazy. the government should step in." source: sam kennedy, "valley feeling pain at the pump," (allentown, pa) morning call, june 21, 2014. suppose the government had stepped in and imposed a price ceiling equal to old price of $3.46 per gallon. a. using the line drawing tool, draw and label the price ceiling. carefully follow the instructions above, and only draw the required object.
Answers: 3
image
Business, 22.06.2019 08:20, auntlynard1843
How much does a neurosurgeon can make most in canada? give me answer in candian dollar
Answers: 1
image
Business, 22.06.2019 20:10, wtwbegay
Mikkelson corporation's stock had a required return of 12.50% last year, when the risk-free rate was 3% and the market risk premium was 4.75%. then an increase in investor risk aversion caused the market risk premium to rise by 2%. the risk-free rate and the firm's beta remain unchanged. what is the company's new required rate of return? (hint: first calculate the beta, then find the required return.) do not round your intermediate calculations.
Answers: 2
You know the right answer?
A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of...

Questions in other subjects: