Variable Costing

Norwood Company has the following information for September:

Sales $380,000
Variable cost of goods sold $182,400
Fixed manufacturing costs $57,000
Variable selling and administrative expenses $34,200
Fixed selling and administrative expenses $2,800

Determine the following for Norwood Company for the month of September:

a. Manufacturing margin $

b. Contribution margin $

c. Income from operations $

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 02:00, zykia1002
Greater concern for innovation and quality has shifted the job trend to using more broadly defined jobs. t/f
Answers: 1
image
Business, 22.06.2019 16:00, ari313
What impact might an economic downturn have on a borrower’s fixed-rate mortgage? a. it might cause a borrower’s payments to go up. b. it might cause a borrower’s payments to go down. c. it has no impact because a fixed-rate mortgage cannot change. d. it has no impact because the economy does not affect interest rates.
Answers: 1
image
Business, 22.06.2019 20:20, caleelwittmann31
This activity is important because as a marketing manager, you must allocate resources to reach your target market. during the strategic marketing process, managers move through three important phases to determine how to optimally allocate resources: a planning phase, an implementation phase, and an evaluation phase. in this interactive exercise, you are asked to review various strategic marketing actions and determine where in the strategic marketing process the action would occur. the goal of this exercise is to demonstrate your understanding of the strategic marketing process and related marketing actions.
Answers: 2
image
Business, 22.06.2019 20:30, Arealbot
Afirm wants to hire a project manager (pm) at a salary of $100,000. 30% of pms have high ability, and 70% of pms have low ability. high ability pms generate $120,000 in revenue and low ability pms generate $80,000 in revenue. in addition to differences in productivity, high and low ability pms have different outside offers. if a high ability pm is not hired by the firm, she can work for another company at a salary of $80,000. if the low ability pm is not hired by the firm, she can work for another company for $70,000. high ability pms are also able to get a project management professional (pmp) certification at a cost of $1,000. low ability pms are unable to get a pmp certification (they would fail the test). the firm is not able to observe a pm’s ability, but is able to observe and verify whether or not the pm has a pmp certificate.(a) draw the extensive form of the game. expert answer
Answers: 3
You know the right answer?
Variable Costing

Norwood Company has the following information for September:

Questions in other subjects:

Konu
Mathematics, 13.01.2020 04:31
Konu
Computers and Technology, 13.01.2020 04:31
Konu
Mathematics, 13.01.2020 04:31
Konu
Health, 13.01.2020 04:31