Consider a palletizer at a bottling plant that has a fi rst cost of $150,000, has operating and maintenance costs of $17,500 per year, and an estimated net salvage value of $25,000 at the end of 30 years. Assume an interest rate of 8 percent/year. What is the future equivalent cost of the investment if the planning horizon is 30 years?

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 02:10, dakodahepps
Materials purchases (on credit). direct materials used in production. direct labor paid and assigned to work in process inventory. indirect labor paid and assigned to factory overhead. overhead costs applied to work in process inventory. actual overhead costs incurred, including indirect materials. (factory rent and utilities are paid in cash.) transfer of jobs 306 and 307 to finished goods inventory. cost of goods sold for job 306. revenue from the sale of job 306. assignment of any underapplied or overapplied overhead to the cost of goods sold account. (the amount is not material.) 2. prepare journal entries for the month of april to record the above transactions.
Answers: 1
image
Business, 22.06.2019 05:10, lorrainetakai1738
Suppose that the free states of eldricia, a small nation, has consumption, investment, government purchases, imports, and exports as follows. consumption $140 investment $50 government purchases $45 imports $30 exports $15 calculate the free states of eldricia's gdp
Answers: 2
image
Business, 22.06.2019 20:50, fathimasaynas2975
Lead time for one of your fastest-moving products is 20 days. demand during this period averages 90 units per day. a) what would be an appropriate reorder point? ) how does your answer change if demand during lead time doubles? ) how does your answer change if demand during lead time drops in half?
Answers: 1
image
Business, 23.06.2019 01:00, gabbytumey
As more people migrated west during the gold rush, what do you think happened to the demand curve in most western markets, holding all else constant? a. there was no shift, nor any increase or decrease in quantity demanded. b. there was no shift, but there was a decrease in quantity demanded. c. the demand curve shifted to the left. d. the demand curve shifted to the right. e. there was no shift, but there was an increase in quantity demanded.
Answers: 2
You know the right answer?
Consider a palletizer at a bottling plant that has a fi rst cost of $150,000, has operating and main...

Questions in other subjects:

Konu
Mathematics, 17.01.2020 17:31