The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of seven days. How much slack does the project have now that Task A is finished

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 18:00, chrismed2001
Emily bought 200 shares of abc co. stock for $29.00 per share on 60% margin. assume she holds the stock for one year and that her interest costs will be $80 over the holding period. ignoring commissions, what is her percentage return (loss) on invested capital if the stock price went down 10%?
Answers: 2
image
Business, 22.06.2019 14:30, Hazy095
Taking commercial paper means the holder acts honestly
Answers: 1
image
Business, 22.06.2019 17:40, gabe2111
Take it all away has a cost of equity of 11.11 percent, a pretax cost of debt of 5.36 percent, and a tax rate of 40 percent. the company's capital structure consists of 67 percent debt on a book value basis, but debt is 33 percent of the company's value on a market value basis. what is the company's wacc
Answers: 2
image
Business, 22.06.2019 21:40, mackenziemelton26
Which of the following is one of the main causes of inflation? a. wages drop so workers have to spend a higher percentage of income on necessities. b. demand drops and forces producers to charge more to meet their costs. c. rising unemployment cuts into national income. d. consumers demand goods faster than they can be supplied.
Answers: 3
You know the right answer?
The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to tak...

Questions in other subjects: