A project manager is managing a project that has reached the end of planning phase. The work scope has been agreed to and definitive cost estimates have been completed for the project. The total estimated cost of the project is $100,000. It is reasonable to expect that the project will not cost over which of the following value?
a. $100,000
b. $110,000
c. $125,000
d. $175,000

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 03:30, shawnplayzsavage
He aldermanalderman company has prepared a sales budget of 42 comma 00042,000 finished units for a 3-month period. the company has an inventory of 10 comma 00010,000 units of finished goods on hand at december 31 and has a target finished goods inventory of 11 comma 00011,000 units at the end of the succeeding quarter. it takes 44 gallons of direct materials to make one unit of finished product. the company has inventory of 64 comma 00064,000 gallons of direct materials at december 31 and has a target ending inventory of 53 comma 00053,000 gallons at the end of the succeeding quarter. how many gallons of direct materials should aldermanalderman company purchase during the 3 months ending march 31? select the labels and enter the amounts to calculate the direct materials (gallons) to be purchased.
Answers: 3
image
Business, 22.06.2019 06:30, hannahroswall1
Ummit record company is negotiating with two banks for a $157,000 loan. fidelity bank requires a compensating balance of 24 percent, discounts the loan, and wants to be paid back in four quarterly payments. southwest bank requires a compensating balance of 12 percent, does not discount the loan, but wants to be paid back in 12 monthly installments. the stated rate for both banks is 9 percent. compensating balances will be subtracted from the $157,000 in determining the available funds in part a. a-1. calculate the effective interest rate for fidelity bank and southwest bank. (do not round intermediate calculations. input your answers as a percent rounded to 2 decimal places.) a-2. which loan should summit accept? southwest bank fidelity bank b. recompute the effective cost of interest, assuming that summit ordinarily maintains $37,680 at each bank in deposits that will serve as compensating balances
Answers: 1
image
Business, 22.06.2019 10:20, alayciaruffin076
What two things do you consider when evaluating the time value of money
Answers: 1
image
Business, 22.06.2019 20:20, 24jgrove
John has served as the chief operating officer (coo) for business graphics, inc., a publicly owned firm, the past 5 years. which of the following statements about john is correct? both john and the ceo of business graphics must certify to the sec that the firm's financial statements are accurate. as the coo, john will be ranked higher than the ceo but still below the cfo. in john's postition as the coo, it is highly unlikely that he would also be the chairperson of the board of directors. as the coo, john would typically be involved with accounting, finance, and asset purchase decisions.
Answers: 2
You know the right answer?
A project manager is managing a project that has reached the end of planning phase. The work scope h...

Questions in other subjects:

Konu
Health, 27.08.2021 22:00