Business, 19.03.2020 21:01 sxbenn

At the end of the third year of a contract, total estimated project cost exceeds the contract price. In both of the first two years, the firm recognized gross profit on the contract under percentage of completion. What is the ending balance in the construction-in-progress account at the beginning of year four on the contract under the percentage-of-completion method (PC), and under the completed-contract method (CC), had that method been used

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 20:30, PerfectMagZ
Abond is issued for less than its face value. which statement most likely would explain why? a. the bond's contract rate is higher than the market rate at the time of the issue. b. the bond's contract rate is the same as the market rate at the time of the issue. c. the bond's contract rate is lower than the market rate at the time of the issue. d. the bond isn't secured by specific assets of the corporation.
Answers: 1
image
Business, 22.06.2019 06:30, henriquetucker
Double corporation acquired all of the common stock of simple company for
Answers: 2
image
Business, 22.06.2019 13:10, Mikey3414
Trey morgan is an employee who is paid monthly. for the month of january of the current year, he earned a total of $4,538. the fica tax for social security is 6.2% of the first $118,500 earned each calendar year, and the fica tax rate for medicare is 1.45% of all earnings for both the employee and the employer. the amount of federal income tax withheld from his earnings was $680.70. his net pay for the month is .
Answers: 1
image
Business, 22.06.2019 19:30, kenz2797
Nextdoor is an instant messaging application for smartphones. new smartphone users find it easier to connect with friends and relatives through this mobile app when compared to other similar instant messaging applications. hence, it has the largest user base in the industry. thus, nextdoor app's value has increased primarily due to itsa. learning curve effects. b. economies of scale. c. economies of scope. d. network effects.
Answers: 2
You know the right answer?
At the end of the third year of a contract, total estimated project cost exceeds the contract price....

Questions in other subjects:

Konu
History, 06.09.2021 15:20
Konu
French, 06.09.2021 15:20