To reduce the duration of a project using CPM, it is necessary to make a reduction on the activity with: a. the largest cost slope on the critical path (CP)b. the smallest cost slope on the CP c. the largest cost slope not on the CP d. the smallest cost slope not on the CP

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 13:40, nina1390
Determine if the following statements are true or false. an increase in government spending can crowd out private investment. an improvement in the budget balance increases the demand for financial capital. an increase in private consumption may crowd out private investment. lower interest rates can lead to private investment being crowded out. a trade balance in sur+ increases the supply of financial capital. if private savings is equal to private investment, then there is neither a budget sur+ nor a budget deficit.
Answers: 1
image
Business, 22.06.2019 16:20, valdezavery1373
The assumptions of the production order quantity model are met in a situation where annual demand is 3650 units, setup cost is $50, holding cost is $12 per unit per year, the daily demand rate is 10 and the daily production rate is 100. the production order quantity for this problem is approximately:
Answers: 1
image
Business, 22.06.2019 19:30, jeanlucceltrick09
Consider the following two projects. both have costs of $5,000 in year 1. project 1 provides benefits of $2,000 in each of the first four years only. the second provides benefits of $2,000 for each of years 6 to 10 only. compute the net benefits using a discount rate of 6 percent. repeat using a discount rate of 12 percent. what can you conclude from this exercise?
Answers: 3
image
Business, 22.06.2019 21:00, nasrah
Dozier company produced and sold 1,000 units during its first month of operations. it reported the following costs and expenses for the month: direct materials $ 69,000 direct labor $ 35,000 variable manufacturing overhead $ 15,000 fixed manufacturing overhead 28,000 total manufacturing overhead $ 43,000 variable selling expense $ 12,000 fixed selling expense 18,000 total selling expense $ 30,000 variable administrative expense $ 4,000 fixed administrative expense 25,000 total administrative expense $ 29,000 required: 1. with respect to cost classifications for preparing financial statements: a. what is the total product cost
Answers: 2
You know the right answer?
To reduce the duration of a project using CPM, it is necessary to make a reduction on the activity w...