A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, the probability that the project will take 224 days or more to complete is.

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 21.06.2019 20:30, danthehero56
Northington, inc. is preparing the company's statement of cash flows for the fiscal year just ended. using the following information, determine the amount of cash flows from operating activities using the indirect method: net income$182,000gain on the sale of equipment12,300proceeds from the sale of equipment92,300depreciation expense—equipment50,000payment of bonds at maturity100,000purchase of land200,000issuance of common stock300,000increase in merchandise inventory35,400decrease in accounts receivable28,800increase in accounts payable23,700payment of cash dividends32,000 $189,400.$332,200.$236,800.$261,400 .$186,800.
Answers: 2
image
Business, 22.06.2019 11:30, jacky852
On average, someone with a bachelor's degree is estimated to earn times more than someone with a high school diploma. a)1.2 b)1.4 c)1.6 d)1.8
Answers: 1
image
Business, 22.06.2019 12:20, lamwil9432
Selected transactions of the carolina company are listed below. classify each transaction as either an operating activity, an investing activity, a financing activity, or a noncash activity. 1. common stock is sold for cash above par value. 2. bonds payable are issued for cash at a discount
Answers: 2
image
Business, 22.06.2019 17:40, lukecoupland4401
Solomon chemical company makes three products, b7, k6, and x9, which are joint products from the same materials. in a standard batch of 320,000 pounds of raw materials, the company generates 70,000 pounds of b7, 150,000 pounds of k6, and 100,000 pounds of x9. a standard batch costs $3,840,000 to produce. the sales prices per pound are $10, $14, and $20 for b7, k6, and x9, respectively. (a) allocate the joint product cost among the three final products using weight as the allocation base. (b) allocate the joint product cost among the three final products using market value as the allocation base. (c) allocate the joint product cost among the three final products using weight as the allocation base.
Answers: 3
You know the right answer?
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the est...

Questions in other subjects:

Konu
Social Studies, 30.09.2020 01:01
Konu
Mathematics, 30.09.2020 01:01
Konu
Mathematics, 30.09.2020 01:01