An activity on a project schedule has these duration estimates: optimistic (a) = 1, most likely (m) = 2, and pessimistic (b) = 5. The activity’s expected duration is:

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 16:10, allisonhall0925
Reliable electric is a regulated public utility, and it is expected to provide steady dividend growth of 5% per year for the indefinite future. its last dividend was $6 per share; the stock sold for $50 per share just after the dividend was paid. what is the company’s cost of equity? (do not round intermediate calculations. enter your answer as a percent rounded to 2 decimal places.)
Answers: 2
image
Business, 22.06.2019 04:00, only1123
Match the type of agreements to their descriptions. will trust living will prenuptial agreement
Answers: 2
image
Business, 22.06.2019 08:40, Damagingawsomeness2
Gerda, a real estate agent, is selling a moderately priced house in a subdivision. she knows from her uncle that the factory being built half a mile from the subdivision will be manufacturing dog food, using a process that creates a very strong odor that permeates the surrounding neighborhood. a buyer, who is unaware of the type of factory under construction, makes an offer on one of the houses gerda is selling, and within a short time, the deal goes through. what does this scenario best illustrate?
Answers: 3
image
Business, 22.06.2019 16:20, milkshakegrande101
There are three factors that can affect the shape of the treasury yield curve (r* t , ip t , and mrp t ) and five factors that can affect the shape of the corporate yield curve (r* t , ip t , mrp t , drp t , and lp t ). the yield curve reflects the aggregation of the impacts from these factors. suppose the real risk-free rate and inflation rate are expected to remain at their current levels throughout the foreseeable future. consider all factors that affect the yield curve. then identify which of the following shapes that the us treasury yield curve can take. check all that apply. a. downward-sloping yield curveb. upward-sloping yield curvec. inverted yield curve
Answers: 1
You know the right answer?
An activity on a project schedule has these duration estimates: optimistic (a) = 1, most likely (m)...

Questions in other subjects:

Konu
English, 23.08.2019 05:30
Konu
History, 23.08.2019 05:30
Konu
Mathematics, 23.08.2019 05:30