A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented below:

Immediate

Activity

Designation

Predecessor

Time in Days

Break down both machines

A

None

3

Clean machine 1

B

A

3

Clean machine 2

C

A

3

Re-set machine 1

D

B

1

Re-set machine 2

E

C

2

Re-calibrate both machines

F

D and E

1

Final test

G

F

2

Using the Single Time Estimate CPM procedure, what is the critical path for the project & the overall project duration?

e. ABCDG & 10 days

c. ABDFG & 10 days

d. ABDFG & 11 days

b. ACEFG & 10 days

a. ACEFG & 11 days

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 04:10, KadaLearns
Universal containers(us) has an integration with its accounting system that creates tens of thousands of orders inside salesforce in a nightly batch. us wants to add automation that can attempt to match leads and contacts to these orders using the email address field on the insert. us is concerned about the performance of the automation with a large data volume. which tool should uc use to automate this process?
Answers: 1
image
Business, 22.06.2019 19:10, jaylene125
Robin hood has hired you as his new strategic consultant to him successfully transform his social change enterprise. robin has told you that he counting on your strategic management knowledge to him and his merrymen achieve their goals. discuss in detail what you think should be robin’s two primary strategic goals and continue by also explaining your analytical reasons that support your recommendations.
Answers: 3
image
Business, 22.06.2019 22:30, jasjas3722
Which of the following describes one of the ways that the demographics of an area affect the price of housing in that area? a. when more people have children, their incomes tend to be higher and the housing prices are also higher. b. older people are more likely to stay in their houses, creating a seller's market that keeps prices low. c. an area with a lower population density won't have enough construction workers to build new houses quickly. d. an area with younger people will have a higher demand for rentals and a lower demand for buying.
Answers: 1
image
Business, 22.06.2019 23:50, Izzyfizzy
Cash flows during the first year of operations for the harman-kardon consulting company were as follows: cash collected from customers, $360,000; cash paid for rent, $44,000; cash paid to employees for services rendered during the year, $124,000; cash paid for utilities, $54,000.in addition, you determine that customers owed the company $64,000 at the end of the year and no bad debts were anticipated. also, the company owed the gas and electric company $2,400 at year-end, and the rent payment was for a two-year period. calculate accrual net income for the year.
Answers: 2
You know the right answer?
A company must perform a maintenance project consisting of seven activities. The activities, their p...

Questions in other subjects:

Konu
Physics, 22.02.2021 07:50