Throughout the performance of the project, some activities will take longer than their estimated duration, others will be done in less time than their estimated duration, and
Select one:
a. many will not be completed.
b. many will take no time to complete.
c. others are to be done by two project teams.
d. a few may conform to the estimated duration exactly.

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 10:10, cuthbertson157
conquest, inc. produces a special kind of light-weight, recreational vehicle that has a unique design. it allows the company to follow a cost-plus pricing strategy. it has $9,000,000 of average assets, and the desired profit is a 10% return on assets. assume all products produced are sold. additional data are as follows: sales volume 1000 units per year; variable costs $1000 per unit; fixed costs $4,000,000 per year; using the cost-plus pricing approach, what should be the sales price per unit?
Answers: 2
image
Business, 22.06.2019 13:30, brittanysanders
1. is the act of declaring a drivers license void and terminated when it is determined that the license was issued through error or fraud.
Answers: 2
image
Business, 22.06.2019 15:10, GreenHerbz206
Paddock pools constructed a swimming pool and deck for the jensens' home. paddock installed the wrong trim on the pool. it would cost $2800 to change the trim-one-fifth of the total cost of the pool. the jensens refuse to pay anything for the pool. the paddock's best defense is: (a) duress (b) substanial performance (c)mistake (d) failure of conditions
Answers: 3
image
Business, 22.06.2019 21:20, alexandriacatro9419
Which of the following best describes the advantage of living in a suburban area? a. suburbs give people access to city jobs along with more living space. b. suburbs give people easy access to cultural attractions and high-paying jobs. c. suburbs have the widest availability of low-cost housing of any living area. d. suburbs have the lowest population density of any living area.
Answers: 1
You know the right answer?
Throughout the performance of the project, some activities will take longer than their estimated dur...

Questions in other subjects:

Konu
Mathematics, 26.10.2021 21:10
Konu
Mathematics, 26.10.2021 21:10
Konu
Mathematics, 26.10.2021 21:10