He following project is at the end of its sixth week. Find the cost and schedule variances. Also, find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the ETC and EAC for the project. Comment on the project status.

Activity Predecessor Duration (wks) Budget ($) Actual Cost ($) %Complete
a - 2 300 400 100
b - 3 200 180 100
c a 2 250 300 100
d a 5 600 400 20
e b, c 4 400 200 20

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 01:40, dperdomo0015
Costs of production that do not change when output changes. question 17 options: total revenuefixed incometotal costfixed cost
Answers: 1
image
Business, 22.06.2019 11:00, sbelgirl2000
Consider an economy where government expenditures are 10 and total tax revenues are 10. the supply of labor is fixed at 125 and the supply of capital is fixed at 8. the economy is described by the following equations. y k to the power of 1 divided by 3 end exponent l to the power of 2 divided by 3 end exponent c 2.5 + 0.75 ( y - t ) i 10 - 0.5 r the level of private savings is
Answers: 1
image
Business, 22.06.2019 15:20, iselloutt4fun
Kelso electric is debating between a leveraged and an unleveraged capital structure. the all equity capital structure would consist of 40,000 shares of stock. the debt and equity option would consist of 25,000 shares of stock plus $280,000 of debt with an interest rate of 7 percent. what is the break-even level of earnings before interest and taxes between these two options?
Answers: 2
image
Business, 22.06.2019 19:30, alejandra340
Adisadvantage of corporations is that shareholders have to pay on profits.
Answers: 1
You know the right answer?
He following project is at the end of its sixth week. Find the cost and schedule variances. Also, fi...

Questions in other subjects:

Konu
English, 02.10.2020 09:01