Assume that you have completed three months of the project. The BAC was $120,000 for this six-month project. You can also make the following assumptions:
PV = $60,000
EV = $55,000
AC = $50,000
What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 16:40, anthonylemus36
Dollywood corporation accumulates the following data concerning a mixed cost, using miles as the activity level. miles driven total cost january 10,000 $16,500 february 8,000 $14,500 march 9,000 $12,500 april 7,000 $12,000 compute the variable and fixed cost elements using the high-low method
Answers: 3
image
Business, 22.06.2019 03:30, 3steves
Diversified semiconductors sells perishable electronic components. some must be shipped and stored in reusable protective containers. customers pay a deposit for each container received. the deposit is equal to the container’s cost. they receive a refund when the container is returned. during 2018, deposits collected on containers shipped were $856,000. deposits are forfeited if containers are not returned within 18 months. containers held by customers at january 1, 2018, represented deposits of $587,000. in 2018, $811,000 was refunded and deposits forfeited were $41,000. required: 1. prepare the appropriate journal entries for the deposits received and returned during 2018. 2. determine the liability for refundable deposits to be reported on the december 31, 2018, balance sheet.
Answers: 1
image
Business, 22.06.2019 20:20, baby851
You are the cfo of a u. s. firm whose wholly owned subsidiary in mexico manufactures component parts for your u. s. assembly operations. the subsidiary has been financed by bank borrowings in the united states. one of your analysts told you that the mexican peso is expected to depreciate by 30 percent against the dollar on the foreign exchange markets over the next year. what actions, if any, should you take
Answers: 2
image
Business, 23.06.2019 09:00, danielahchf
Jorge is attending college next year. he just got information on the college costs and the financial aid package the college is offering. jorge knows his parents can contribute $4,500 each year. jorge’s college costs & financial aid package per year costs financial aid package tuition & fees grants & scholarship $26,000 $18,500 room & board work-study $12,500 $8,500 how much will jorge need to pay each year from his own savings and from loans? $3,000 $7,000 $7,500 $11,500
Answers: 2
You know the right answer?
Assume that you have completed three months of the project. The BAC was $120,000 for this six-month...

Questions in other subjects:

Konu
Chemistry, 08.02.2021 19:00