Cost of Units Completed and in Process
The charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production.
Work in Process—Assembly Department
Bal., 1,600 units, 35% completed 17,440 To Finished Goods, 29,600 units ?
Direct materials, 29,000 units @ $9.50 275,500
Direct labor 84,600
Factory overhead 39,258
Bal. ? units, 45% completed ?
a. Based on the above data, determine the different costs listed below.
1. Cost of beginning work in process inventory completed this period. $
2. Cost of units transferred to finished goods during the period. $
3. Cost of ending work in process inventory. $
4. Cost per unit of the completed beginning work in process inventory, rounded to the nearest cent. $
b. Did the production costs change from the preceding period?
Yes
No
Yes
c. Assuming that the direct materials cost per unit did not change from the preceding period, did the The rate used to allocate costs between completed and partially completed production. conversion costs per equivalent unit increase, decrease, or remain the same for the current period?

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 20.06.2019 18:04, kate460
Hello, could you answer this question for me? if management wishes to know how well a business's inventory is moving, they could use the a. acid test ratio. b. inventory turnover. c. accounts receivable turnover. d. current ratio.
Answers: 1
image
Business, 22.06.2019 00:20, angelcat9137
Overspeculation and a decrease in consumer confidence are both leading factors of: ?
Answers: 1
image
Business, 22.06.2019 15:00, Jocelynrichards
Why entrepreneurs start businesses. a) monopolistic competition b) perfect competition c) sole proprietorship d) profit motive
Answers: 1
image
Business, 22.06.2019 19:00, makaylahunt
James is an employee in the widget inspection department of xyz systems, a government contractor. james was part of a 3-person inspection team that found a particular batch of widgets did not meet the exacting requirements of the u. s. government. in order to meet the tight deadline and avoid penalties under the contract, james' boss demanded that the batch of widgets be sent in fulfillment of the government contract. when james found out, he went to the vice president of the company and reported the situation. james was demoted by his boss, and no longer works on government projects. james has a:
Answers: 3
You know the right answer?
Cost of Units Completed and in Process
The charges to Work in Process—Assembly Department for...

Questions in other subjects:

Konu
English, 25.06.2021 20:20
Konu
Mathematics, 25.06.2021 20:20