Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the six tasks that make up the job are 4, 6, 7, 2, 6, and 5 minutes, and the cycle time is 10 minutes?
A. 3.
B. 5.
C. 6.
D. 8.
E. None of the above.

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 10:40, jonnaevans4856
You were able to purchase two tickets to an upcoming concert for $100 apiece when the concert was first announced three months ago. recently, you saw that stubhub was listing similar seats for $225 apiece. what does it cost you to attend the concert?
Answers: 1
image
Business, 22.06.2019 14:00, tamariarodrigiez
How many months does the federal budget usually take to prepare
Answers: 1
image
Business, 22.06.2019 19:10, sierravick123owr441
You have just been hired as a brand manager at kelsey-white, an american multinational consumer goods company. recently the firm invested in the development of k-w vision, a series of systems and processes that allow the use of up-to-date data and advanced analytics to drive informed decision making about k-w brands. it is 2018. the system is populated with 3 years of historical data. as brand manager for k-w’s blue laundry detergent, you are tasked to lead the brand's turnaround. use the vision platform to to develop your strategy and grow blue’s market share over the next 4 years.
Answers: 2
image
Business, 22.06.2019 21:30, sergiom6185
Russell's study compared gpa of those students who volunteered for academic study skills training and those who did not elect to take the training. he found that those who had the training also had higher gpa. with which validity threat should russell be most concerned?
Answers: 2
You know the right answer?
Using the assembly-line balancing procedure, which of the following is the theoretical minimum numbe...

Questions in other subjects:

Konu
Mathematics, 07.07.2020 02:01