Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion.
PV = $65,000
EV = $58,000
AC = $68,000
BAC = $155,000
a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
d. Use the SPI to estimate how long it will take to finish this project.
Answers: 2
Business, 21.06.2019 23:30, enchantednights
Renaldo scanlon is a financial consultant. he earns $30 per hour and works 32.5 hours a week. what is his straight-time pay?
Answers: 1
Business, 22.06.2019 11:40, Josias13
In early january, burger mania acquired 100% of the common stock of the crispy taco restaurant chain. the purchase price allocation included the following items: $4 million, patent; $3 million, trademark considered to have an indefinite useful life; and $5 million, goodwill. burger mania's policy is to amortize intangible assets with finite useful lives using the straight-line method, no residual value, and a five-year service life. what is the total amount of amortization expense that would appear in burger mania's income statement for the first year ended december 31 related to these items?
Answers: 2
Business, 22.06.2019 22:30, wbrandi118
The answer here, x=7, is not in the interval that you selected in the previous part. what is wrong with the work shown above?
Answers: 1
Business, 22.06.2019 22:40, juicecarton
Effective capacity is the: a. capacity a firm expects to achieve given the current operating constraints. b. minimum usable capacity of a particular facility. c. sum of all the organization's inputs. d. average output that can be achieved under ideal conditions. e. maximum output of a system in a given period.
Answers: 1
Given the following information for a one-year project, answer the following questions. Recall that...
Mathematics, 10.06.2021 05:50
Spanish, 10.06.2021 05:50
History, 10.06.2021 05:50
English, 10.06.2021 05:50
Mathematics, 10.06.2021 05:50