You are creating a schedule duration estimate for the activities in the PDR Project. You’re working with your project and comparing the results of a past similar project to predict the time of the current project. What estimating approach are you using?
A. Organizational process assets
B. Parametric
C. Analogous
D. PERT

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 21.06.2019 14:30, jessebeck0805
At which level will a manager use analytics to make decisions? operational level managerial level strategic level all of the above
Answers: 3
image
Business, 21.06.2019 16:40, anthonylemus36
Dollywood corporation accumulates the following data concerning a mixed cost, using miles as the activity level. miles driven total cost january 10,000 $16,500 february 8,000 $14,500 march 9,000 $12,500 april 7,000 $12,000 compute the variable and fixed cost elements using the high-low method
Answers: 3
image
Business, 21.06.2019 18:00, chrismed2001
Emily bought 200 shares of abc co. stock for $29.00 per share on 60% margin. assume she holds the stock for one year and that her interest costs will be $80 over the holding period. ignoring commissions, what is her percentage return (loss) on invested capital if the stock price went down 10%?
Answers: 2
image
Business, 22.06.2019 22:20, ciara180
Which of the following is correct? a. a tax burden falls more heavily on the side of the market that is more elastic. b. a tax burden falls more heavily on the side of the market that is less elastic. c. a tax burden falls more heavily on the side of the market that is closer to unit elastic. d. a tax burden is distributed independently of the relative elasticities of supply and demand.
Answers: 1
You know the right answer?
You are creating a schedule duration estimate for the activities in the PDR Project. You’re working...

Questions in other subjects:

Konu
Biology, 03.12.2019 19:31