A construction project is broken down into the following 10 activities:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
1 — 5
2 1 2
3 1 5
4 1 6
5 2, 3 5
6 3 5
7 4 2
8 5 5
9 6, 7 6
10 8, 9 4

a. What is the critical path?
b. How many weeks will the project take to complete?
c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which activities would you shorten to cut the project by four weeks?

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 08:00, lizisapenguin
Why do police officers get paid less than professional baseball players?
Answers: 2
image
Business, 22.06.2019 10:00, silviamgarcia
Scenario: you have advised the owner of bond's gym that the best thing to do would be to raise the price of a monthly membership. the owner wants to know what may happen once this price increase goes into effect. what will most likely occur after the price of a monthly membership increases? check all that apply. current members will pay more per month. the quantity demanded for memberships will decrease. the number of available memberships will increase. the owner will make more money. bond's gym will receive more membership applications.
Answers: 1
image
Business, 22.06.2019 11:30, iBrain
4.     chef a says that broth should be brought to a boil. chef b says that broth should be kept at an even, gentle simmer. which chef is correct? a. neither chef is correct. b. chef a is correct. c. both chefs are correct. d. chef b is correct. student c   incorrect which is right answer
Answers: 2
image
Business, 22.06.2019 12:50, DesperatforanA
Demand increases by less than supply increases. as a result, (a) equilibrium price will decline and equilibrium quantity will rise. (b) both equilibrium price and quantity will decline. (c) both equilibrium price and quantity will rise
Answers: 3
You know the right answer?
A construction project is broken down into the following 10 activities:

ACTIVITY IMMEDIA...

Questions in other subjects:

Konu
Mathematics, 17.09.2020 05:01
Konu
Mathematics, 17.09.2020 05:01
Konu
Mathematics, 17.09.2020 05:01
Konu
Mathematics, 17.09.2020 05:01
Konu
History, 17.09.2020 05:01
Konu
Biology, 17.09.2020 05:01
Konu
History, 17.09.2020 05:01
Konu
Mathematics, 17.09.2020 05:01
Konu
Mathematics, 17.09.2020 05:01
Konu
Mathematics, 17.09.2020 05:01