Project which is about to start consists of activities listed below:-Activity Immediate Predecessor Duration
A None 4 B A 13 C A 5 D C 11 E C 3 F D, E 4 G None 3 H A, G 5 I G 4 J H 17 K H 2 L J, K 3 M F, L 3 N B, M 3 O L, M 2 P O 3 Q N, P 4
The project should be completed by the end of week 38. If the project is delayed beyond this date, it estimated that it will cost the firm Kshs. 30,000 a week
i) Draw a network to represent the project and determine the critical path.
ii) What is the earliest time at which the project can be completed and what penalty cost, if any, will be incurred?
iii) Activity K is a two-week course to train new salesmen. The hotel which will be used for the course has been booked for weeks 12 and 13. In the light of your analysis, should this booking be change
Answers: 2
Business, 22.06.2019 00:40, lindseybug
Guardian inc. is trying to develop an asset-financing plan. the firm has $450,000 in temporary current assets and $350,000 in permanent current assets. guardian also has $550,000 in fixed assets. assume a tax rate of 40 percent. a. construct two alternative financing plans for guardian. one of the plans should be conservative, with 70 percent of assets financed by long-term sources, and the other should be aggressive, with only 56.25 percent of assets financed by long-term sources. the current interest rate is 12 percent on long-term funds and 7 percent on short-term financing. compute the annual interest payments under each plan.
Answers: 3
Business, 22.06.2019 06:30, Shavaila18
Select all that apply. what do opponents of minimum wage believe are the results of minimum wage? increases personal income results in job shortages causes unemployment raises prices of goods
Answers: 1
Business, 22.06.2019 21:30, anthonybowie99
What term is used to describe the outsourcing of logistics? a. shipper managed inventoryb. hollow logistics(smi)c. sub-logisticsd. e-logisticse. third-party logistics (3pl)
Answers: 1
Project which is about to start consists of activities listed below:-Activity Immediate Predecessor...
Mathematics, 14.10.2019 04:30
Mathematics, 14.10.2019 04:30
Physics, 14.10.2019 04:30
Chemistry, 14.10.2019 04:30
Chemistry, 14.10.2019 04:30
History, 14.10.2019 04:30
Social Studies, 14.10.2019 04:30