Afirm produces and sells two products, plus and max. the following information is available relating to setup costs (a part of factory overhead):
plus max
units produced 200 16,000
batch size (units) 10 400
number of setups 20 40
direct labor hours per unit 5 5
total direct labor hours 1,000 80,000
cost per setup $1,080
total setup cost $64,800
1. with traditional two-stage allocation of overhead costs, using direct labor hours as the allocation base, the setup cost portion of overhead that is allocated to each unit of product for plus and max, respectively is

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 16:00, idcbrooo
Sarah borrowed $16,500 on may 23 with interest due on september 3. if the interest rate is 9%, find the interest on the loan using exact interest and ordinary interest.
Answers: 2
image
Business, 22.06.2019 01:30, Arealbot
The strength of the economy depends on the balance pf production and consumption of goods and consumption of goods and services
Answers: 1
image
Business, 22.06.2019 03:00, autumn8668
Afirm's before-tax cost of debt, rd, is the interest rate that the firm must pay on debt. because interest is tax deductible, the relevant cost of debt used to calculate a firm's wacc is the cost of debt, rd (1 – t). the cost of debt is used in calculating the wacc because we are interested in maximizing the value of the firm's stock, and the stock price depends on cash flows. it is important to emphasize that the cost of debt is the interest rate on debt, not debt because our primary concern with the cost of capital is its use in capital budgeting decisions. the rate at which the firm has borrowed in the past is because we need to know the cost of capital. for these reasons, the on outstanding debt (which reflects current market conditions) is a better measure of the cost of debt than the . the on the company's -term debt is generally used to calculate the cost of debt because more often than not, the capital is being raised to fund -term projects. quantitative problem: 5 years ago, barton industries issued 25-year noncallable, semiannual bonds with a $1,600 face value and a 8% coupon, semiannual payment ($64 payment every 6 months). the bonds currently sell for $845.87. if the firm's marginal tax rate is 40%, what is the firm's after-tax cost of debt? round your answer to 2 decimal places. do not round intermediate calcu
Answers: 3
image
Business, 22.06.2019 05:30, AjTruu2880
Laurelton heating & cooling installs and services commercial heating and cooling systems. laurelton uses job costing to calculate the cost of its jobs. overhead is allocated to each job based on the number of direct labor hours spent on that job. at the beginning of the current year, laurelton estimated that its overhead for the coming year would be $ 61 comma 500. it also anticipated using 4 comma 100 direct labor hours for the year. in april comma laurelton started and completed the following two jobs: (click the icon to view the jobs.) laurelton paid a $ 20-per-hour wage rate to the employees who worked on these two jobs. read the requirements requirement 1. what is laurelton's predetermined overhead rate based on direct labor hours? determine the formula to calculate laurelton's predetermined overhead rate based on direct labor hours, then calculate the rate. / = predetermined overhead rate
Answers: 2
You know the right answer?
Afirm produces and sells two products, plus and max. the following information is available relating...

Questions in other subjects:

Konu
Mathematics, 19.04.2021 21:00
Konu
Geography, 19.04.2021 21:00