When terminating a project for capital budgeting purposes, the working capital outlay required at the initiation of the project will

a. decrease the terminal cash flow because it is a historical cost.

b. not affect the terminal cash flow.

c. increase the terminal cash flow because it is recaptured.

d. decrease the terminal cash flow because it is an outlay.

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 11:10, AM28
Your team has identified the risks on the project and determined their risk score. the team is in the midst of determining what strategies to put in place should the risks occur. after some discussion, the team members have determined that the risk of losing their network administrator is a risk they'll just deal with if and when it occurs. although they think it's a possibility and the impact would be significant, they've decided to simply deal with it after the fact. which of the following is true regarding this question? a. this is a positive response strategy. b. this is a negative response strategy. c. this is a response strategy for either positive or negative risk known as contingency planning. d. this is a response strategy for either positive or negative risks known as passive acceptance.
Answers: 2
image
Business, 22.06.2019 16:30, tadams9922
Penelope summers received certain income benefits in 2018. she received $1,400 of state unemployment insurance benefits, $2,000 from a federal unemployment trust fund and $3,700 workers’ compensation received for an occupational injury. what amount of the compensation must penelope include in her income
Answers: 1
image
Business, 22.06.2019 16:30, allytrujillo20oy0dib
Summarize the specific methods used by interest groups in order to influence governmental decisions making in all three branches of government. provide at least two examples from each branch.
Answers: 3
image
Business, 22.06.2019 22:00, tydukes10
"jake’s roof repair has provided the following data concerning its costs: fixed cost per month cost per repair-hour wages and salaries $ 20,900 $ 15.00 parts and supplies $ 7.70 equipment depreciation $ 2,800 $ 0.35 truck operating expenses $ 5,720 $ 1.60 rent $ 4,690 administrative expenses $ 3,850 $ 0.50 for example, wages and salaries should be $20,900 plus $15.00 per repair-hour. the company expected to work 2,600 repair-hours in may, but actually worked 2,500 repair-hours. the company expects its sales to be $47.00 per repair-hour. required: compute the company’s activity variances for may."
Answers: 1
You know the right answer?
When terminating a project for capital budgeting purposes, the working capital outlay required at th...

Questions in other subjects:

Konu
Biology, 24.03.2020 18:39
Konu
Mathematics, 24.03.2020 18:39