Cpm
a. assumes we do not know ahead of time what activities must be completed.
b. assumes that activity time estimates follow the normal probability distribution.
c. is a network technique that allows three time estimates for each activity in a project.
d. is a deterministic network technique that allows for project crashing.

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 19:30, cbaldwin6605
Consider the following ethical argument. which of the three statements represents the moral statement about a moral principle? statement 1: a dealership advertised a car at a very low price, but only had a similar higher priced model in stock. statement 2: it is wrong to perform a bait and switch. statement 3: the dealership was wrong to advertise the car on special sale when in actually it was not available.
Answers: 3
image
Business, 22.06.2019 05:30, adazeb2003
Find a company that has followed a strong strategic direction- state that generic strategy and the back-up points to support your position.
Answers: 1
image
Business, 22.06.2019 17:30, gghkooo1987
An essential element of being receptive to messages is to have an open mind true or false
Answers: 2
image
Business, 22.06.2019 18:00, theflash077
Large public water and sewer companies often become monopolies because they benefit from although the company faces high start-up costs, the firm experiences average production costs as it expands and adds more customers. smaller competitors would experience average costs and would be less
Answers: 1
You know the right answer?
Cpm
a. assumes we do not know ahead of time what activities must be completed.
b. assu...

Questions in other subjects:

Konu
Mathematics, 10.12.2019 20:31
Konu
Social Studies, 10.12.2019 20:31