Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadline. she has calculated the crash cost per unit and knows the maximum units each activity can be reduced. what is the next step?

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 11:00, mmcdaniels46867
Companies hd and ld are both profitable, and they have the same total assets (ta), total invested capital, sales (s), return on assets (roa), and profit margin (pm). both firms finance using only debt and common equity. however, company hd has the higher total debt to total capital ratio. which of the following statements is correct? a) company hd has a higher assets turnover than company ld. b) company hd has a higher return on equity than company ld. c) none of the other statements are correct because the information provided on the question is not enough. d) company hd has lower total assets turnover than company ld. e) company hd has a lower operating income (ebit) than company ld
Answers: 2
image
Business, 22.06.2019 16:50, tayveon122
Identify and describe a variety of performance rating scales that can be used in organizations including graphical scales, letter scales, and numeric scales.
Answers: 2
image
Business, 22.06.2019 20:30, allakhalilpea0zc
Caleb construction (cc) incurs supervisor salaries expense in the construction of homes. if cc manufactures 100 homes in a year, fixed supervisor salaries will be $400,000. with the current construction supervisors, cc's productive capacity is 150 homes in a year. however, if cc is contracts to build more than 150 homes per year, it will need to hire additional supervisors, which are hired as full-time rather than temporary employees. cc's productive capacity would then become 200 homes per year, and salaries expense would increase to $470,000. how would cc’s salaries expense be properly classified? fixed variable mixed stepped curvilinear
Answers: 3
image
Business, 22.06.2019 21:00, nikkiwoodward1ovgszp
Warner inc. sells a high-speed retrieval system for mining information. it provides the following information for the year. budgeted actual overhead cost $965,700 $905,000 machine hours 58,570 49,200 direct labor hours 107,300 104,200 overhead is applied on the basis of direct labor hours. compute the predetermined overhead rate. predetermined overhead rate $ per direct labor hour link to text determine the amount of overhead applied for the year. the amount of overhead applied $
Answers: 1
You know the right answer?
Emily has recently learned that she needs to reduce the duration of her project to meet an imposed d...

Questions in other subjects: