In a garments factory, a part requires 0.10 hours of labor per unit in work center b and 1 hour of setup time. the planned order release (order size) for a week is 2000 units.
which of the following is the capacity requirement for a week at work center b?
a. 101b. 151c. 201d. 251
Answers: 3
Business, 21.06.2019 23:50, amandajennings01
Juan has a retail business selling skateboard supplies he maintains large stockpiles of every item he sells in a warehouse on the outskirts of town he keeps finding that he has to reorder certain supplies all the time but others only once a year how can he solve this problem?
Answers: 1
Business, 22.06.2019 23:30, lulustar13
Atelephone call center uses three customer service representatives (csrs) during the 8: 30 a. m. to 9: 00 a. m. time period. the standard service rate is 3.0 minutes per telephone call per csr. assuming a target labor utilization rate of 80 percent, how many calls can these three csrs handle during this half-hour period?
Answers: 1
Business, 23.06.2019 00:30, humpty21
One of the growers is excited by this advancement because now he can sell more crops, which he believes will increase revenue in this market. as an economics student, you can use elasticities to determine whether this change in price will lead to an increase or decrease in total revenue in this market. using the midpoint method, the price elasticity of demand for soybeans between the prices of $5 and $4 per bushel is , which means demand is between these two points. therefore, you would tell the grower that his claim is because total revenue will as a result of the technological advancement.
Answers: 1
In a garments factory, a part requires 0.10 hours of labor per unit in work center b and 1 hour of s...
Mathematics, 25.03.2020 20:39
Mathematics, 25.03.2020 20:39
History, 25.03.2020 20:39
Mathematics, 25.03.2020 20:39