Acontractor estimated that his 10-men crew could complete the construction in 110 days if there was no rain. (assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). however, after 5 days of rain, on the 61-st day, he hired 6 more people to finish the project early. if the job was done in 100 days, on how many days after day 60 was it raining? (a) 4(b) 5(c) 6(d) 7(e) 8

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 06:30, henriquetucker
Double corporation acquired all of the common stock of simple company for
Answers: 2
image
Business, 22.06.2019 11:00, aiueo946
Aprofessional does specialized work that's primarily: degree based. medical or legal. well paying. intellectual and creative
Answers: 2
image
Business, 22.06.2019 14:50, kianofou853
Ann chovies, owner of the perfect pasta pizza parlor, uses 20 pounds of pepperoni each day in preparing pizzas. order costs for pepperoni are $10.00 per order, and carrying costs are 4 cents per pound per day. lead time for each order is three days, and the pepperoni itself costs $3.00 per pound. if she were to order 80 pounds of pepperoni at a time, what would be the average inventory level?
Answers: 3
image
Business, 22.06.2019 19:00, mazolethrin3461
The following are budgeted data: january february march sales in units 16,200 22,400 19,200 production in units 19,200 20,200 18,700 one pound of material is required for each finished unit. the inventory of materials at the end of each month should equal 20% of the following month's production needs. purchases of raw materials for february would be budgeted to be:
Answers: 3
You know the right answer?
Acontractor estimated that his 10-men crew could complete the construction in 110 days if there was...

Questions in other subjects: