Business, 27.11.2019 06:31 Animallover100
Using pert, adam munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 4.
a) what is the probability that the project will be completed in 17 months?
b) what is the probability that the project will be completed in 20 months?
c) what is the probability that the project will be completed in 23 months?
d) what is the probability that the project will be completed in 25 months?
e) what is the due date that yields a 95% chance of completion?
Answers: 2
Business, 22.06.2019 01:20, Adolfosbaby
As a project manager for a large construction company, shaun decided to make the performance appraisal process as painless as possible for his crew. he spent a considerable amount of time creating performance standards he felt were reasonable, and after six months' time, he scheduled individual appointments with each worker to discuss strengths and weaknesses and areas that needed improvement according to the standards he privately set. some employees were sent to vestibule training, and one even got a promotion with additional compensation. what did he fail to do correctly
Answers: 2
Business, 22.06.2019 09:40, Tyrant4life
Henry crouch's law office has traditionally ordered ink refills 55 units at a time. the firm estimates that carrying cost is 35% of the $11 unit cost and that annual demand is about 240 units per year. the assumptions of the basic eoq model are thought to apply. for what value of ordering cost would its action be optimal? a) for what value of ordering cost would its action be optimal?
Answers: 2
Business, 22.06.2019 11:30, pettygirl13
Florence invested in a factory requiring. federally-mandated reductions in carbon emissions. how will this impact florence as the factory's owner? a. her factory will be worth less once the upgrades are complete. b. her factory will likely be bought by the epa. c. florence will have to invest a large amount of capital to update the factory for little financial gain. d. florence will have to invest a large amount of capital to update the factory for a large financial gain.
Answers: 1
Using pert, adam munson was able to determine that the expected project completion time for the cons...
Biology, 04.12.2020 20:20
English, 04.12.2020 20:20
History, 04.12.2020 20:20
English, 04.12.2020 20:20
Biology, 04.12.2020 20:20