Prepare a master schedule given this information: it is now the end of week 1; customer orders are 25 for week 2, 16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. use the mps rule of ordering production when projected on-hand inventory would be negative without production. suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used.

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 21.06.2019 19:50, kennrecklezz
Which of the following best explains why treasury bonds have an effect on the size of the money supply? a. the amount of treasury bonds in circulation affects both unemployment and inflation. b. the government can spend more money and charge lower taxes by using treasury bonds. c. the federal reserve bank can buy and sell these bonds to raise or lower bank deposits. d. the interest paid on treasury bonds influences the interest rates charged by private banks. 2b2t
Answers: 1
image
Business, 21.06.2019 23:30, shannydouglas
Which type of market are you in if your company, along with three other companies, controls 95 percent of the total music industry?
Answers: 3
image
Business, 22.06.2019 02:30, damiangibson2
Question 1 which of the following tasks use your roommate as a resource? choose all answers which apply. take order wash the mixer’s bowl and mix the dough spoon cookies onto the tray unload the cookies from the oven pack the cookies 1 points question 2 which of the following tasks use the tray(s) as a resource? choose all answers which apply. take order wash the mixer’s bowl and mix the dough bake the cookies cool the cookies accept payment 1 points question 3 determine the task time for the following tasks. fill integer numbers into the blank (e. g., 5 rather than 5.0) wash and mixing the dough: minute(s)/order spoon cookies onto the tray: minute(s)/order set up timer: minute(s)/order bake: minute(s)/order cool the cookies: minute(s)/order pack the cookies: minute(s)/order accept payment: minute(s)/order 2 points question 4 q4: determine the cycle time for the following resources. fill integer numbers into the blank (e. g., 5 rather than 5.0) kristen (you): minute(s) roommate: minute(s) oven: minute(s) 2 points question 5 what is the capacity rate (in orders/hour) of the roommate? 1 points question 6 what is the capacity rate (in orders/hour) of the whole process? 2 points question 7 how long (in minutes) it takes to process the first order?
Answers: 3
image
Business, 22.06.2019 08:40, Damagingawsomeness2
Gerda, a real estate agent, is selling a moderately priced house in a subdivision. she knows from her uncle that the factory being built half a mile from the subdivision will be manufacturing dog food, using a process that creates a very strong odor that permeates the surrounding neighborhood. a buyer, who is unaware of the type of factory under construction, makes an offer on one of the houses gerda is selling, and within a short time, the deal goes through. what does this scenario best illustrate?
Answers: 3
You know the right answer?
Prepare a master schedule given this information: it is now the end of week 1; customer orders are...

Questions in other subjects:

Konu
History, 26.06.2019 13:50