Steve is fairly cautious when analyzing a new project and thus he projects the most optimistic, the most realistic, and the most pessimistic outcome that can reasonably be expected. which type of analysis is steve using?

simulation testing.

scenario analysis.

rationing analysis.

sensitivity analysis.

break-even analysis

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 17:10, DroctorWellsfan
All else being equal, which is true about a firm with high operating leverage relative to a firm with low operating leverage? select one: a. a higher percentage of the high operating leverage firm's costs are fixed. b. the high operating leverage firm is exposed to less risk. c. the debt payments limit the high operating leverage firm's opportunities to turn a big profit. d. the high operating leverage firm has more debt.
Answers: 2
image
Business, 21.06.2019 21:20, ninilizovtskt
“wonderful! not only did our salespeople do a good job in meeting the sales budget this year, but our production people did a good job in controlling costs as well,” said kim clark, president of martell company. “our $11,150 overall manufacturing cost variance is only 3% of the $1,536,000 standard cost of products made during the year. that’s well within the 3% parameter set by management for acceptable variances. it looks like everyone will be in line for a bonus this year.” the company produces and sells a single product. the standard cost card for the product follows: standard cost card—per unit direct materials, 4.00 feet at $4.00 per foot $ 16.00 direct labor, 1.1 direct labor-hours at $13 per direct labor-hour 14.30 variable overhead, 1.1 direct labor-hours at $2.40 per direct labor-hour 2.64 fixed overhead, 1.1 direct labor-hours at $6.50 per direct labor-hour 7.15 standard cost per unit $ 40.09the following additional information is available for the year just completed: a. the company manufactured 20,000 units of product during the year. b. a total of 77,000 feet of material was purchased during the year at a cost of $4.25 per foot. all of this material was used to manufacture the 20,000 units. there were no beginning or ending inventories for the year. c. the company worked 24,000 direct labor-hours during the year at a direct labor cost of $12.50 per hour. d. overhead is applied to products on the basis of standard direct labor-hours. data relating to manufacturing overhead costs follow: denominator activity level (direct labor-hours) 19,000 budgeted fixed overhead costs $ 123,500 actual variable overhead costs incurred $ 64,800 actual fixed overhead costs incurred $ 120,900required: 1. compute the materials price and quantity variances for the year. (round standard price and actual price to 2 decimal places. indicate the effect of each variance by selecting "f" for favorable, "u" for unfavorable, and "none" for no effect (i. e., zero 2. compute the labor rate and efficiency variances for the year. (round standard rate and actual rate to 2 decimal places. indicate the effect of each variance by selecting "f" for favorable, "u" for unfavorable, and "none" for no effect (i. e., zero 3. for manufacturing overhead compute: a. the variable overhead rate and efficiency variances for the year. (round standard rate and actual rate to 2 decimal places. indicate the effect of each variance by selecting "f" for favorable, "u" for unfavorable, and "none" for no effect (i. e., zero b. the fixed overhead budget and volume variances for the year. (indicate the effect of each variance by selecting "f" for favorable, "u" for unfavorable, and "none" for no effect (i. e., zero
Answers: 2
image
Business, 22.06.2019 04:10, chloeholt123
What is the difference between secure bonds and naked bonds?
Answers: 1
image
Business, 22.06.2019 07:30, davidleew24
Jewelry manufacturers produce a range of products such as rings, necklaces, bracelets, and brooches. what fundamental economic question are they addressing by offering this range of items?
Answers: 3
You know the right answer?
Steve is fairly cautious when analyzing a new project and thus he projects the most optimistic, the...

Questions in other subjects:

Konu
Mathematics, 06.06.2020 05:57