Athird method for determining the forecasted cost at completion is to re-estimate the costs for all the remaining work to be performed and then add this re-estimate to the cumulative actual cost. if the amount of cumulated actual costs is less than difference between the total budgeted cost and the re-estimate, then
a. the fcac is less than the tbc.
b. the fcac is greater than the tbc.
c. the fcac cannot be calculated with the values given.
d. additional information is needed to predict the fcac.

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 19:40, heroicblad
Sean has placed a job ad and is now interviewing potential employees. which of the following questions is he legally allowed to ask during the interview? do you have any disabilities that will require special accommodation? how many children do you have? where did you earn your degree and how has it prepared you for this position? is this your maiden name that you have listed on the job application?
Answers: 2
image
Business, 22.06.2019 16:40, kat1191
Job applications give employers uniform information for all employees, making it easier to
Answers: 1
image
Business, 23.06.2019 00:00, SoccerHalo
Todd and jim learned that in building a business plan, it was important for them to:
Answers: 1
image
Business, 23.06.2019 03:30, nae878
What does the term "smalling up" mean, according to white? what ways have you or people you know had to "small up"? if you haven't, what ways could you?
Answers: 2
You know the right answer?
Athird method for determining the forecasted cost at completion is to re-estimate the costs for all...

Questions in other subjects:

Konu
Mathematics, 24.06.2021 01:00
Konu
Mathematics, 24.06.2021 01:00
Konu
Mathematics, 24.06.2021 01:00
Konu
SAT, 24.06.2021 01:00