Aproject schedule has been updated. the activity placement of spread footing concrete was originally scheduled to begin as early as day 10. the activity duration is 4 days. the actual start day was day 12. the original schedule had a calculated total float of 7 days for this activity. the recalculated total float for the activity, when updated, would be . 2 days
b. 5 days
c. 6 days
d. 9 days

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 15:00, queensquishy2004
Do you have to get teased in the police academy?
Answers: 1
image
Business, 21.06.2019 18:50, toshahoskins0098
You are the manager of a firm that produces output in two plants. the demand for your firm's product is p = 20 − q, where q = q1 + q2. the marginal costs associated with producing in the two plants are mc1 = 2 and mc2 = 2q2. how much output should be produced in plant 1 in order to maximize profits?
Answers: 3
image
Business, 21.06.2019 21:00, 3steves
Do you think a travel organization company might be able to get less expensive airline tickets then you as an individual could get? (no less then 25 words)
Answers: 1
image
Business, 22.06.2019 06:00, kinglightskin2k
If you miss two payments on a credit card what is generally the penalty
Answers: 1
You know the right answer?
Aproject schedule has been updated. the activity placement of spread footing concrete was originally...

Questions in other subjects:

Konu
Mathematics, 06.04.2020 18:38