You work for a large manufacturing plant. your firm is thinking of initiating a new project to release an overseas product line. this is the company's first experience in the overseas market, and it wants to make a big splash with the introduction of this product. the project entails producing your product in a concentrated formula and packaging it in smaller containers than the u. s. product uses. a new machine is needed in order to mix the first set of ingredients in the concentrated formula. which of the following actions is the next best step the project manager should take?
a. the project manager should document the project's high-level requirements in a project charter document and recommend that the project proceed.
b. the project manager knows the project is a go and should document the description of the product in the statement of work.
c. the project manager should document the business need for the project and recommend that a feasibility study be performed to determine the viability of the project.
d. the project manager should document the needs and demands that are driving the project in a business case document.

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 21.06.2019 21:30, AquariusOx
Price and efficiency variances, journal entries. the schuyler corporation manufactures lamps. it has set up the following standards per finished unit for direct materials and direct manufacturing labor: direct materials: 10 lb. at $4.50 per lb. $45.00 direct manufacturing labor: 0.5 hour at $30 per hour 15.00 the number of finished units budgeted for january 2017 was 10,000; 9,850 units were actually produced. actual results in january 2017 were as follows: direct materials: 98,055 lb. used direct manufacturing labor: 4,900 hours $154,350 assume that there was no beginning inventory of either direct materials or finished units. during the month, materials purchased amounted to 100,000 lb., at a total cost of $465,000. input price variances are isolated upon purchase. input-efficiency variances are isolated at the time of usage. 1. compute the january 2017 price and efficiency variances of direct materials and direct manufacturing labor. 2. prepare journal entries to record the variances in requirement 1. 3. comment on the january 2017 price and efficiency variances of schuyler corporation. 4. why might schuyler calculate direct materials price variances and direct materials efficiency variances with reference to different points in time
Answers: 2
image
Business, 22.06.2019 00:00, kyllow5644
Which of the following is a disadvantage to choosing a sole proprietorship business structure? question 9 options: the owner has personal responsibility for the company's liabilities. the owner has to share the profits with partners. the owner is still liable for personal debts. the owner has to report to shareholders.
Answers: 1
image
Business, 22.06.2019 10:00, joy8348
Which term best fits the sentence? is the process of reasoning, analyzing, and making important decisions. it’s an important skill in making career decisions. a. critical thinking b. weighing pros and cons c. goal setting
Answers: 1
image
Business, 22.06.2019 10:30, batmanmarie2004
The card shoppe needs to maintain 21 percent of its sales in net working capital. currently, the store is considering a four-year project that will increase sales from its current level of $349,000 to $408,000 the first year and to $414,000 a year for the following three years of the project. what amount should be included in the project analysis for net working capital in year 4 of the project?
Answers: 3
You know the right answer?
You work for a large manufacturing plant. your firm is thinking of initiating a new project to relea...

Questions in other subjects: