In a resource-constrained project, the first priority in assigning resources is usually given to activities with the
a. smallest duration
b. least slack
c. most slack
d. lowest identification number
e. highest cost

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 21:40, brooket30057
Morgana company identifies three activities in its manufacturing process: machine setups, machining, and inspections. estimated annual overhead cost for each activity is $168,000, $315,900, an $97,200, respectively. the cost driver for each activity and the expected annual usage are number of setups 2,100, machine hours 24,300, and number of inspections 1,800. compute the overhead rate for each activity. machine setups $ per setup machining $ per machine hour inspections $ per inspection
Answers: 1
image
Business, 22.06.2019 15:40, arigamez90
Aprice control is: question 1 options: a)a tax on the sale of a good that controls the market price. b)an upper limit on the quantity of some good that can be bought or sold. c)a legal restriction on how high or low a price in a market may go. d)control of the price of a good by the firm that produces it.
Answers: 1
image
Business, 22.06.2019 15:50, fireemblam101ovu1gt
Evaluate a real situation between two economic actors; it could be any scenario: two competing businesses, two countries in negotiations, two kids trading baseball cards, you and another person involved in an exchange or anything else. use game theory to analyze the situation and the outcome (or potential outcome). be sure to explain the incentives, benefits and risks each face.
Answers: 1
image
Business, 22.06.2019 16:20, tristan4233
Carlos hears juan and rita’s complaints about the new employees with whom they have to work with, as well as their threats to quit the company. if carlos were to reassign juan and rita to new, unique roles and separate them from the ronny and bill, it would signal that carlos has moved into the stage of managing resistance.
Answers: 3
You know the right answer?
In a resource-constrained project, the first priority in assigning resources is usually given to act...

Questions in other subjects:

Konu
Mathematics, 16.07.2019 08:10