Suppose you have a project with four tasks as follows: task 1 can start immediately and has a duration of 2. task 2 can start after task 1 is completed and has an estimated duration of 4. task 3 can start after task 2 has been completed and has an estimated duration of 5. task 4 can start after task 1 is completed and must be completed when task 3 is completed. its estimated duration is 8. what is the length of the critical path for this project? 9 10 11 12

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 00:50, yolo123321
Cool beans is a locally owned coffee shop that competes with two large coffee chains, planeteuro and frothies. alicia, the owner, hired two students to count the number of customers that entered each of the coffee shops to estimate what percent of people who are interested in coffee are visiting each shop. after a week, the students found the following results: 589 visited cool beans, 839 visited planeteuro, and 1,290 visited frothies. the students were surprised that cool beans had 139 visits on monday which represented 59% of all people who visited one of the three coffee shops on mondays. how many people visited one of the three coffee shops during the week?
Answers: 2
image
Business, 22.06.2019 03:00, nyahdrake
You are the manager of the packaging department in a cookie factory. (obviously, the packaging employees cannot eat the cookies that are transferred in during the period.) after your employees insert cookies into colorful packages (step 1) for display on store shelves, the packages of cookies are then boxed using cardboard cartons (step 2) for shipment to stores. each unit of product is represented by a carton of packaged cookies. the packaging department began the period with 1,000 units of cookies. during the period, 5,000 units of cookies were transferred in from the baking department and 5,500 units of cookies were transferred out to the finished goods department. the number of units of cookies in the ending inventory of the packaging department equals:
Answers: 1
image
Business, 22.06.2019 11:10, nat8475
The prebisch–singer hypothesis concludes that: a. technology lowers the cost of manufactured products, so developing countries should see an increase in their terms of trade. b. developing countries experience a long-run decline in their terms of trade, as the demand for primary products in higher-income countries declines relative to their demand for manufactured goods. c. because of unfair trading practices, labor in developing countries is exploited. d. opec has been responsible for a slowdown in the world's standard of living.
Answers: 3
image
Business, 22.06.2019 11:40, berlyntyler
Select the correct answer brian wants to add a chart to his dtp project. what is the best way he can do this? a draw the chart using the dtp program draw option b create the chart in a spreadsheet then import it c. use the dtp chart wizard to create the chart within the dtp d. create an image of the chart in an image editor then import the image e use html code to create a chart within the dtp program
Answers: 3
You know the right answer?
Suppose you have a project with four tasks as follows: task 1 can start immediately and has a durat...

Questions in other subjects:

Konu
Arts, 12.11.2020 07:00