Given the following information for a one-year project, answer the following questions. • planned value (pv) = $30,000 • earned value (ev) = $27,000 • actual cost (ac) = $25,000 • budget at completion (bac) = $150,000 1. what is the cost variance, schedule variance, cost performance index, and schedule performance index for the project? 2. is the project ahead of schedule or behind schedule? 3. is the project under budget or over budget? 4. use the cost performance index to calculate the estimate at completion (eac) for this project. is the project performing better or worse than planned? 5. use the schedule performance index to estimate how long it will take to finish this project.

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 22:10, jaxonsensintaff
Arival company manufactures fuel tanks for cars using a different production technique. the total weekly cost (in dollars) of producing x tanks is given by c(x) = 10000 +90x - 0.04x2 find the marginal cost at a production level of 500 fuel tanks per week to approximate the cost of the 501st unit (round to the nearest 2 decimal places, if needed)
Answers: 3
image
Business, 22.06.2019 10:00, bob7220
Your father offers you a choice of $120,000 in 11 years or $48,500 today. use appendix b as an approximate answer, but calculate your final answer using the formula and financial calculator methods. a-1. if money is discounted at 11 percent, what is the present value of the $120,000?
Answers: 3
image
Business, 22.06.2019 23:30, sierravick123owr441
An outside supplier has offered to sell talbot similar wheels for $1.25 per wheel. if the wheels are purchased from the outside supplier, $15,000 of annual fixed overhead could be avoided and the facilities now being used could be rented to another company for $45,000 per year. direct labor is a variable cost. if talbot chooses to buy the wheel from the outside supplier, then annual net operating income would:
Answers: 1
image
Business, 23.06.2019 00:00, makayyafreeman
According to the video, the gross national product had declined from $104 billion in 1929 to about in 1933.
Answers: 2
You know the right answer?
Given the following information for a one-year project, answer the following questions. • planned va...

Questions in other subjects: