Shrieves casting company is considering adding a new line to its product mix, and the capital budgeting analysis is being conducted by sidney johnson, a recently graduated mba. the production line would be set up in unused space in the main plant. the machinery’s invoice price would be approximately $200,000, another $10,000 in shipping charges would be required, and it would cost an additional $30,000 to install the equipment. the machinery has an economic life of 4 years, and shrieves has obtained a special tax ruling that places the equipment in the macrs 3-year class. the machinery is expected to have a salvage value of $25,000 after 4 years of use. the new line would generate incremental sales of 1,250 units per year for 4 years at an incremental cost of $100 per unit in the first year, excluding depreciation. each unit can be sold for $200 in the first year. the sales price and cost are both expected to increase by 3% per year due to inflation. further, to handle the new line, the firm’s net working capital would have to increase by an amount equal to 12% of sales revenues. the firm’s tax rate is 40%, and its overall weighted average cost of capital, which is the risk-adjusted cost of capital for an average project (r), is 10%. define “incremental cash flow.” (1) should you subtract interest expense or dividends when calculating project cash flow?

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 12:00, elianagilbert3p3hh63
Areal estate agent is considering changing her cell phone plan. there are three plans to choose from, all of which involve a monthly service charge of $20. plan a has a cost of $.42 a minute for daytime calls and $.17 a minute for evening calls. plan b has a charge of $.52 a minute for daytime calls and $.15 a minute for evening calls. plan c has a flat rate of $80 with 275 minutes of calls allowed per month and a charge of $.38 per minute beyond that, day or evening. a. determine the total charge under each plan for this case: 150 minutes of day calls and 70 minutes of evening calls in a month. (do not round intermediate calculations. round your answer to 2 decimal places. omit the "$" sign in your response.)c. if the agent will use the service for daytime calls, over what range of call minutes will each plan be optimal? (round each answer to the nearest whole number. include the indifference point itself in each answer.)d. suppose that the agent expects both daytime and evening calls. at what point (i. e., percentage of total call minutes used for daytime calls) would she be indifferent between plans a and b?
Answers: 1
image
Business, 22.06.2019 12:10, latdoz0952
Which of the following is not part of the mission statement of the department of homeland security? lead the unified national effort to secure america protect against and respond to threats and hazards to the nation ensure safe and secure borders coordinate intelligence operations against terrorists in other countries
Answers: 1
image
Business, 22.06.2019 19:10, lizzlegnz999
After the price floor is instituted, the chairman of productions office buys up any barrels of gosum berries that the producers are not able to sell. with the price floor, the producers sell 300 barrels per month to consumers, but the producers, at this high price floor, produce 700 barrels per month. how much producer surplus is created with the price floor? show your calculations.
Answers: 2
image
Business, 22.06.2019 20:30, Arealbot
Afirm wants to hire a project manager (pm) at a salary of $100,000. 30% of pms have high ability, and 70% of pms have low ability. high ability pms generate $120,000 in revenue and low ability pms generate $80,000 in revenue. in addition to differences in productivity, high and low ability pms have different outside offers. if a high ability pm is not hired by the firm, she can work for another company at a salary of $80,000. if the low ability pm is not hired by the firm, she can work for another company for $70,000. high ability pms are also able to get a project management professional (pmp) certification at a cost of $1,000. low ability pms are unable to get a pmp certification (they would fail the test). the firm is not able to observe a pm’s ability, but is able to observe and verify whether or not the pm has a pmp certificate.(a) draw the extensive form of the game. expert answer
Answers: 3
You know the right answer?
Shrieves casting company is considering adding a new line to its product mix, and the capital budget...