Details of a PERT/CPM problem is listed in the table below. Times are given in weeks. Activity Preceding Optimistic Time Probable Time Pessimistic Time A -- 7 9 14 B A 2 2 8 C A 8 12 16 D A 3 5 10 E B 4 6 8 F B 6 8 10 G C, F 2 3 4 H D 2 2 8 I H 6 8 16 J G, I 4 6 14 K E, J 2 2 5 a.​Calculate the expected time & variance for each activity. Enter these values in the appropriate column in the table above. {10 Marks} b. ​Which activities form the critical path? {3 Marks} c. ​What is the estimated time of the critical path? {3 Marks} d. ​What are the project variance and the project standard deviation? {4 Marks} e. ​What is the probability of completion of the project after week 40? {5 Marks}

ansver
Answers: 2

Other questions on the subject: Advanced Placement (AP)

image
Advanced Placement (AP), 23.06.2019 11:50, naysia2006
Willing to give brainliest + free points answer quickly a tire without good traction has less a. grip on the road b. grip on the axle c. air in it d. risk of exploding
Answers: 2
image
Advanced Placement (AP), 24.06.2019 01:30, cassiemyers60
What is the quickest way to resolve problems from a supply shock?
Answers: 1
image
Advanced Placement (AP), 25.06.2019 22:00, ayaan9573
When your organs don't receive enough blood, they begin to a. shut down b. speed up c. inflame d. dry out
Answers: 2
image
Advanced Placement (AP), 26.06.2019 00:00, brenyasanders6238
Atown located beside a river derives a large percentage of its revenues each year from the local logging industry. however, heavy traffic to and from the logging sites has increased pollution and contributed to soil erosion. this has also resulted in the loss of native bird species in the logged forests. which of the following is the most sustainable solution to this problem? protecting certain forested areas to allow the birds to recover relocating the equipment and vehicles to new forests for logging relocating the birds to new forests away from the town introducing new bird species to replace the species that have been lost reducing the number of trucks traveling through the forest by 10 percent
Answers: 2
You know the right answer?
Details of a PERT/CPM problem is listed in the table below. Times are given in weeks. Activity Prece...

Questions in other subjects:

Konu
Computers and Technology, 04.12.2020 21:20